Tangshan Jiecheng Energy Co., Ltd. construction project


According to the relevant requirements of "Several Measures to Support the Smooth Operation of domestic waste incineration Power Generation Enterprises in Hebei Province" jointly issued by Hebei Provincial Department of Housing and Urban-Rural Development, Hebei Provincial Development and Reform Commission and Hebei Provincial Department of Ecological and Environmental Protection (Ji Jian Urban Management [2022] No. 14), Tangshan Jiecheng Energy Co., Ltd. has prepared the "Analysis of Non-material Changes in the Construction Project of Tangshan Jiecheng Energy Co., LTD." (hereinafter referred to as the "non-material changes") and determined that the project is not a major change. Our company is now to publicize the "non-significant change explanation", and our company promises to be responsible for the authenticity of the publicity time.

The analysis of non-material changes is disclosed

According to the relevant requirements of "Several Measures to Support the Smooth Operation of domestic waste incineration Power Generation Enterprises in Hebei Province" jointly issued by Hebei Provincial Department of Housing and Urban-Rural Development, Hebei Provincial Development and Reform Commission and Hebei Provincial Department of Ecological and Environmental Protection (Ji Jian Urban Management [2022] No. 14), Tangshan Jiecheng Energy Co., Ltd. has prepared the "Analysis of Non-material Changes in the Construction Project of Tangshan Jiecheng Energy Co., LTD." (hereinafter referred to as the "non-material changes") and determined that the project is not a major change. Our company is now to publicize the "non-significant change explanation", and our company promises to be responsible for the authenticity of the publicity time.

I. Basic information of the project

The 4# incinerator of Tangshan Jiecheng Energy Co., Ltd. is a mechanical stoker with a daily processing capacity of 600 tons of garbage and 300 tons of sludge, with an external steam supply of 103,000 t/a and supporting environmental protection facilities. The flue gas treatment process is: SNCR+PNCR+ dry and semi-dry deacidification + liquid alkali deacidification + activated carbon adsorption + cloth bag dust removal.

In order to solve some general industrial solid waste disposal problems, the 4# incinerator of Jiecheng Company intends to burn combustible general industrial solid waste without recycling value. The nature of this part of the general industrial solid waste is similar to domestic waste, including waste textiles, waste leather products, waste wood products, waste paper, waste rubber products, waste plastic products, waste composite packaging, etc. After the change of the project, the 4# incinerator is designed to feed 600t/d of domestic waste, 90t/d of sludge and 210t/d of general industrial solid waste.

2. Contact person and contact information

Construction unit: Tangshan Jiecheng Energy Co., LTD

Contact: horse worker

Contact: 17692594840

 

Tangshan Jiecheng Energy Co., LTD

October 12, 2022